Fresnillo And MAG Silver Provide Juanicipio Commissioning Update

Alleen voor leden beschikbaar, wordt daarom gratis lid!

Algemeen advies 27/12/2021 15:46
Fresnillo plc (“Fresnillo”) and MAG Silver Corp. (“MAG Silver”) today provide a commissioning update on the Juanicipio Project (56% / 44% Fresnillo and MAG Silver, respectively).

The Juanicipio Project team delivered the Project for plant commissioning on schedule despite the recent changes to labour contracting legislation and having successfully mitigated most COVID-19 related issues over the past two years, a testament to the dedication of the operational and development teams on the ground.

However, the ‘Comisión Federal de Electricidad’ (“CFE”), the state-owned electrical company, has just notified Fresnillo, the Juanicipio Project operator, that approval to complete the tie-in to the national power grid cannot yet be granted and the mill commissioning timeline will therefore be extended by approximately six months. This is directly related to knock-on effects of the pandemic on the CFE’s operations, predominantly related to a lack of CFE staff which limits its ability to oversee three key tasks to: review the existing installation; supervise physical connection to the active power grid; and approve required blackout prevention devices.

As operator, Fresnillo will continue to engage closely with the CFE and ‘El Centro Nacional de Control de Energía’ (“CENACE”) to do all that it can to expedite these necessary approvals. Although there remains uncertainty regarding the timing for connecting the Juanicipio Project to the power grid, the current estimate, which continues to be subject to potential COVID-19 related realities, is that full load commissioning activities will be approved sometime after the first week of May 2022.

Stoping and mineralized mine development at Juanicipio will continue. In order to minimize any potential adverse effect, Fresnillo will make available any unused plant capacity at its Minera Fresnillo and Minera Saucito operations to process mineralized material produced at Juanicipio during this period, and if possible matching commissioning and ramp up tonnages that were previously expected. The effect on cashflow generation from Juanicipio therefore will also be mitigated while CFE approvals are pending.

“As an industry, we continue to manage the ongoing impact of the pandemic and while frustrating for all concerned, we recognize this situation is beyond the control of all parties,” said Octavio Alvidrez, Chief Executive of Fresnillo plc. “The health and safety of our people and all our partners remains our priority. We thank the CFE for their engagement and will continue to work closely with them to accelerate grid connection as quickly as we can. Meanwhile, we will continue to process mineralized development material by using any excess capacity available at the Minera Fresnillo and Minera Saucito plants, minimizing any impact on future cashflow generation.”

“We are very fortunate to be able to process mineralized material from Juanicipio through the excess capacity available at the Minera Fresnillo and Minera Saucito plants, which should minimize the economic impact of the electrical connection timing,” said George Paspalas, President and CEO of MAG Silver. “The Juanicipio Project team has managed through stringent COVID-19 protocols to make the process plant effectively ready for start-up. However, approvals for the electrical connection for the Project have been affected by governmental COVID-19 restrictions that have severely limited the CFE in carrying out their reviews and final sign-off. We look forward to the CFE resuming normal activities, so we can flip the switch on our plant!”

About Fresnillo plc

Fresnillo plc is the world's largest primary silver producer and Mexico's largest gold producer, listed on the London and Mexican Stock Exchanges under the symbol FRES.

Fresnillo plc has seven operating mines, all of them in Mexico - Fresnillo, Saucito, Ciénega (including the San Ramón satellite mine, Las Casas Rosario & Cluster Cebollitas), Herradura, Soledad-Dipolos1, Noche Buena and San Julián (Veins and Disseminated Ore Body), three development projects - the Pyrites Plant at Fresnillo, the optimisation of the beneficiation plant also at Fresnillo and Juanicipio, and three advanced exploration projects – Rodeo, Orisyvo and Guanajuato, as well as a number of other long term exploration prospects.

Fresnillo plc has mining concessions and exploration projects in Mexico, Peru and Chile.

Fresnillo plc has a strong and long tradition of exploring, mining, a proven track record of mine development, reserve replacement, and production costs in the lowest quartile of the cost curve for silver.

Fresnillo plc's goal is to maintain the Group's position as the world's largest primary silver company and Mexico’s largest gold producer.

1 Operations at Soledad-Dipolos are currently suspended.

For further information, please visit our website: www.fresnilloplc.com or contact:

Fresnillo plc
London Office
Gabriela Mayor, Head of Investor Relations.Patrick Chambers



Beperkte weergave !
Leden hebben toegang tot meer informatie! Omdat u nog geen lid bent of niet staat ingelogd, ziet u nu een beperktere pagina. Wordt daarom GRATIS Lid of login met uw wachtwoord


Copyrights © 2000 by XEA.nl all rights reserved
Niets mag zonder toestemming van de redactie worden gekopieerd, linken naar deze pagina is wel toegestaan.


Copyrights © DEBELEGGERSADVISEUR.NL