October 21, 2024, Vancouver, BC – Taseko Mines Limited (TSX: TKO; NYSE MKT: TGB; LSE: TKO) ("Taseko" or the "Company") is pleased to provide a progress update for construction activities at its Florence Copper project.

To-date, approximately 300,000 project hours have been worked and there have been no reportable injuries or environmental incidents. There are currently 280 construction personnel at site. All activities are advancing on schedule and as of September 30, 2024, the project is approaching 40% complete. First copper production is still anticipated in the fourth quarter 2025.

Since construction commenced earlier this year, the bulk of activities have been focused on earthworks, concrete, and wellfield drilling. Installation of structural steel, tanks, and process equipment is now underway.

Summary of key activities and status as of September 30, 2024:

Earthworks and site preparation for the plant area and commercial wellfield – ~75% complete
Concrete foundations for SX/EW plant and associated infrastructure – ~50% complete
Pre-assembly and installation of structural steel for the solvent extraction plant commenced in August
Installation of process equipment commenced in September
Powerline installation – ~65% complete
Wellfield drilling – a total of 34 production wells completed to date, out of a total of 90 to be drilled during the construction phase
Point of compliance well drilling – 9 wells completed to date, out of a total of 18
Construction of process and surface water runoff ponds
Hiring permanent operating staff – 75 of 170 total positions and all but one key management position has been filled
Stuart McDonald, President & CEO of Taseko, commented, “We are pleased with progress through the first nine months of construction. With approximately 75% of total construction costs now committed, we expect total costs to be within 10-15% of the original US$232 million* estimate. The project remains on track for first copper production in late 2025, which will be a transformative event for our Company.”

see & read more on
https://www.tasekomines.com/investors/news/taseko-mines-provides-construction-update-for-florence-copper/



Beperkte weergave !
Leden hebben toegang tot meer informatie! Omdat u nog geen lid bent of niet staat ingelogd, ziet u nu een beperktere pagina. Wordt daarom GRATIS Lid of login met uw wachtwoord


Copyrights © 2000 by XEA.nl all rights reserved
Niets mag zonder toestemming van de redactie worden gekopieerd, linken naar deze pagina is wel toegestaan.


Copyrights © DEBELEGGERSADVISEUR.NL