Highlights:
First gold pour is on track for Q4 2025, key long lead items procured
Project Development team appointed, led by Chief Development Officer Dimitrios Felekis
Engineering for doubling plant capacity to 6Mtpa was awarded to Primero Engineering and is currently 24% complete
Additional Ball Mill awarded and scheduled for shipment in May 2025, SAG Mill on track for Q1 2025
Power station awarded with delivery from May 2025
Tailings Storage Facility (TSF) expanded design commenced with Knight PiƩsold
Civils contracts awarded, and concrete work has recommenced on site
Earthworks Fleet for TSF and infrastructure arrived in Guinea
Electrical and instrumentation awarded to ECG Engineering
Inferred resource drilling program for Mansounia nearing completion with more than 32,000 metres of RC and more than 2,600 meters of DD completed
Updated Feasibility Study for Kiniero on track for Q1 2025, led by AMC.