MONTAGE GOLD REPORTS ON ITS Q2 AND H1-2025 ACTIVITIES

Alleen voor leden beschikbaar, wordt daarom gratis lid!

Overig advies 13/08/2025 16:06
Koné project construction on-budget and well on-schedule • Strong continued exploration focus • Robust liquidity sources
CONSTRUCTION ACTIVITIES
› Over 3.0 million hours worked without a Lost Time Injury, with more than 2,500 employees and contractors on-site
› Well on track for first gold pour in Q2-2027 and on budget with over $370 million of capital committed as at today,
representing approximately 44% of the total capital expenditure, with prices in line with expectations
› Rapid progress achieved on key process plant activities including the ball mill foundations, pre-leach and tailings
thickeners, with notably the start of CIL tank erection occurring 2 months ahead of schedule which marks a key milestone
› Other key infrastructure is well advanced including the river abstraction facility, TSF, relocation site, and plant buildings,
while the water storage facility was completed and is already holding water
EXPLORATION ACTIVITIES
› 2025 exploration programme increased from 90,000 to 120,000 meters, with 83,280 meters already drilled in H1-2025,
focused on delineating higher-grade resources with the goal of supplementing production from the onset
› Step-out and in-fill drilling is underway at all 7 new higher-grade satellite deposits for which starter maiden resources
were published in early 2025, whilst drilling progressed on the 6 targets which were advanced to pre-resource stage
› Maiden resources for new discoveries and updated resources for the recently made discoveries are expected to be
published throughout the year
FINANCIAL POSITION
› Robust liquidity and available sources of financing totalling $735 million compared to remaining capital disbursements of
$676 million
Vancouver, Canada — August 12, 2025 — Montage Gold Corp. (“Montage” or the “Company”) (TSX: MAU, OTCQX: MAUTF) is
pleased to report on its construction and exploration activities for Q2-2025, with highlights provided in Table 1 below.

see & read more on
https://www.montagegold.com/_resources/news/2025/20250812_Montage-Gold-Reports-on-Q2-and-H1-2025-Activities.pdf



Beperkte weergave !
Leden hebben toegang tot meer informatie! Omdat u nog geen lid bent of niet staat ingelogd, ziet u nu een beperktere pagina. Wordt daarom GRATIS Lid of login met uw wachtwoord


Copyrights © 2000 by XEA.nl all rights reserved
Niets mag zonder toestemming van de redactie worden gekopieerd, linken naar deze pagina is wel toegestaan.


Copyrights © DEBELEGGERSADVISEUR.NL