Rio Tinto provides Iron Ore update following Tropical Cyclone Sean

Alleen voor leden beschikbaar, wordt daarom gratis lid!

Overig advies 24/01/2025 07:07
PERTH, Australia--(BUSINESS WIRE)-- Tropical Cyclone Sean delivered record rain along parts of the Pilbara coastline of Western Australia, impacting Rio Tinto rail and port operations.

A railcar dumper at the East Intercourse Island (EII) port facility, which shipped 45 million tonnes of total Rio Tinto Iron Ore shipments in 2024, was flooded after the weather event passed the coast, delivering 274mm to Karratha on 20 January 2025.

Assessments are ongoing. Initial indications suggest the dumper at EII could be offline for three to four weeks, as rectifications works are required to repair flood damage.

Recovery works within the broader Iron Ore system are progressing, with the majority of rail and port operations now returned to operations.

The company is working to mitigate impacts and will provide an update at its full year results on 19 February 2025.

First quarter shipments will be affected. Overall shipment guidance for 2025 remains unchanged.

View source version on businesswire.com: https://www.businesswire.com/news/home/20250123264417/en/




Beperkte weergave !
Leden hebben toegang tot meer informatie! Omdat u nog geen lid bent of niet staat ingelogd, ziet u nu een beperktere pagina. Wordt daarom GRATIS Lid of login met uw wachtwoord


Copyrights © 2000 by XEA.nl all rights reserved
Niets mag zonder toestemming van de redactie worden gekopieerd, linken naar deze pagina is wel toegestaan.


Copyrights © DEBELEGGERSADVISEUR.NL